Project Overview
- Owner: American Municipal Power
- Project Cost: $6,396,012
- Project Complete: September 2011 – March 2013
![Meldahl Hydroelectric Powerhouse 1](https://aquariusmarine.net/wp-content/uploads/2017/02/Meldahl-Hydroelectric-Powerhouse-1-1.jpg)
![Meldahl Hydroelectric Powerhouse 2](https://aquariusmarine.net/wp-content/uploads/2017/02/Meldahl-Hydroelectric-Powerhouse-2.jpg)
![Meldahl Hydroelectric Powerhouse 3](https://aquariusmarine.net/wp-content/uploads/2017/02/Meldahl-Hydroelectric-Powerhouse-3.jpg)
![](https://aquariusmarine.net/wp-content/uploads/2017/02/Meldahl-Hydroelectric-Powerhouse-4.jpg)
This project, located in Willowgrove, Kentucky at Captain Anthony Meldahl Locks and Dam on the Ohio River, included dredging, excavation, and riprap placement for a future hydroelectric power plant. Working as a subcontractor to Alberici-Baker Joint Venture, Aquarius Marine dredged and excavated over 1 million yards of material and placed 400,000 tons of rip rap.
.